2020 Tech Refresh CAP Project

9 %

Status

Project is 9 % complete, starting on Mon 7/27/20 and ending on Thu 6/30/22.

In Process [In Process]

9% complete, updated on Tue 4/27/21 3:25 PM by Fabio Zampieri

Changed Percent Complete from 5% to 9%.
Ordered switches and developing timeline to install.
Prioritizing the deployment of new computers.

Details

Dates
Mon 7/27/20 - Thu 6/30/22
Acct/Dept
IIT Director
Service
Project Requests / Project Request
Type
Teaching and Learning / Classroom Technology and Support
Health
Green - On track
Classification
Business Continuity/Maintenance
Created
Fri 10/16/20 10:28 AM
Modified
Wed 9/22/21 4:53 PM

Description

The goal is to make the best use of available Tech Refresh CAP Project funds, expending them where it is the most necessary and looking at options other than simply replacing equipment.

This plan is in keeping with the 2018 HP Desktop Computer Mid-life Upgrade Project as it continues the practice of upgrading existing systems to prolong their useful life. This should lead to a deferral in computer replacement purchases for a number of years.

Goals

  1. Tech Plan - Address technology refresh needs

  2. Tech Plan - Enhance Educational Technology Resources

Risks

  1. Medium Resource Bottlenecks

    The major dependencies include funding and staff availability.

Manager

Alternate Manager(s)

Sponsor

Stakeholders (5)

ES
Erik Skinner
VP Administrative Services
Informed
To be informed
Tue 10/20/20 2:20 PM
JT
James Todd
Vice President Student Serv
Informed
informed
Tue 10/20/20 2:20 PM
PY
Phil Yorde
Mgr Technical Support Svcs
Responsible
Project Manager
Fri 9/4/20 5:52 PM
RB
Rebecca Bocchicchio
Vice President Instruction
Informed
informed
Tue 10/20/20 2:20 PM
RD
Ryan Davis
Vice President Human Resources
Informed
informed
Tue 10/20/20 2:21 PM